DESSA were engaged to design a scheme for the bridge refurbishment works. Careful planning was required to ensure the Plettac Futuro scaffold could be installed around the bridge members, whilst providing a clear run for the DESSA sysTRAX to operate.
Three roofs of 60m lengths were then lifted in modules, by crane onto the sysTRAX. This gave the user a combined 180m of coverage that could be moved as necessary along a 350m long bridge. DESSA 450 alloy beams were installed below for form a mobile working platform for access.





| Date: | October 2019 |
| Duration: | 1 year |
| Customer: | TD-S |
| Provision: | Design and Supply |
| System: | UNI Roof, sysTRAX, 450 alloy series |
| Span: | 14m |
| Length: | 3x60m |
| Build Method: | Craned onto sysTRAX |