Altrix roof erected using the DESSA beam support assembly, with a 36 degree pitch to allow for a reduction in the scaffold levels at either side of the build.




Facts & Figures
| Date: | November 2016 |
| Duration: | 8 months |
| Customer: | Altrad Plettac Mefran |
| Provision: | Supply |
| System: | Altrix (APM exclusive design) |
| Span: | 15m 36 degree Duopitch |
| Length: | 20m (2.5m bays) |
| Build Method: | Crane, to fixed roof support |